PROJECT CASE STUDY - Serie 1 met Soundshield scherm en randbeveiliging
Naam project: Premier Inn Extension Scarborough
Projectlocatie: Scarborough, UK
Opdrachtgever: PDR Construction
Opdrachtsom: £ 16 000,00
Productomschrijving: Serie 1 platform met 1,6 m hoog geluidscherm
Overzicht: Dit 42m² Series 1 Platform met Soundshield Screen omranding aan twee zijden werd geleverd om de geluidoverlast voor de buren van de 10 Mitsubishi VRV-units op dit project te beperken.
PROJECT CASE STUDY - Serie 1 met Acoustic+ en standaard scherm
Projectnaam: St James University Hospital, Pathologielaboratorium - Leeds
Projectlocatie: Leeds, West Yorkshire
Opdrachtgever: BAM Construction Ltd - North East
Opdrachtsom: £ 185 000,00
Product Description: Series 1 platform with 3m high Acoustic+ screens with access landing and flue support structure.
Overview: Our solution eliminated a 200mm think concrete slab at roof height with all associated costs in time and hassle and allowed the roof to continue through over the complete area, significantly shortening the time it took to get the building to the watertight stage. With a total weight of 6 tonne instead of approximately 25-30 tonne this was a huge saving on the environment and well as the structural requirements. The complete 217m² 5kPa rated roof plant enclosure was installed in less than 2 weeks, with a crane required for one day only.
PROJECT CASE STUDY - Serie 1 met Peacemaker en overkapping voor installaties
Projectnaam: 22 Wyvil Road
Locatie van het project: Londen
Opdrachtgever: Kuropatwa Ltd
Opdrachtsom: £ 38 000,00
Product Description: Series 1 Platform with Peacemaker enclosure and roofed plantroom with no gaps to slats
Overview: This solution fulfilled the requirement of having air conditioning condensers needing airflow on one part of the platform and other equipment that needed to be in a plantroom. This complete structure was assembled in 2 days with the materials being brought to the roof via a materials hoist, as the site was very congested and would have required a road closure for a crane.
PROJECT CASE STUDY - Serie 1 met Acoustic+ en plafondbeugels
Project: Lewisham Exchange Studentenhuisvesting
Locatie van het project: Lewisham, Londen
Client: Tide Construction
Opdrachtsom: £ 17 000,00
Product Description: Series 1 platform with 2m high Acoustic+ screens
Overview: Due to the very constrained space down the side of the tallest modular building in the world this Acoustic+ enclosure was designed with overhead bracing to avoid having internal post braces. The base and sides were fabricated offsite to reduce the on-site build time to 3 hours.
PROJECT CASE STUDY - Serie 1 met Peacemaker scherm en lamellendak
Project: 3-5 Crutched Friars
Locatie van het project: Londen
Client: Zentura
Waarde: £ 19 000,00
Product Description: Series 1 platform with 2m Peacemaker screens and Louvred Roof
Overview: This acoustic enclosure was built off site and lifted to the roof as a completed unit. The louvred roof was removable and was lifted off to allow the 5 Daikin VRV units to be lifted into the enclosure.
PROJECT CASE STUDY - Serie 2 met randbeveiliging
Locatie van het project: Hereford, UK
Opdrachtgever: Integra Buildings/MTX Contracts
Opdrachtsom: £ 17 000,00
Productomschrijving: Serie 2 platform met relingen
Overview: This Series 2 platform replaced a large structural steel deck that was initially planned and saved many roof penetrations. This platform and guardrail surround was installed in just 1 day.
Project CASE STUDY - Serie 2 met randbeveiliging en loopbrug
Project: Cheltenham General Hospital
Projectlocatie: Cheltenham, UK
Client: Bairstow’s Mechanical Services
Value: £ 18 000.00
Product Description: Series 2 platform with Guardrails and access walkway
Overview: This Series Platform provided for the mounting of 2 large units as well as an access walkway and stairs. Covering 2 roof levels our agile system could accommodate this and provide one level working surface for a large heat pump installation.
PROJECT CASE STUDY – Series 2 with Standard Screen
Project: Herinrichting Joods Huis
Projectlocatie: Gibraltar
Opdrachtgever: Interbuild gi
Value: £ 10 000.00
Product Description: Series 2 platform with 1.6m high Standard Screen
Overview: This 16m² Series 1 Platform with Standard Screen surround was supplied in kit form on one single pallet, with individual parts manually lifted to the roof and installed in 4 hours while training a Spanish installation team.
PROJECT CASE STUDY - Serie 2 met Soundshield
Projectnaam: James Paget University Hospital
Projectlocatie: Great Yarmouth, UK
Opdrachtgever: Eco Modular
Opdrachtsom: £ 38 000,00
Productomschrijving: Serie 2 platform met Soundshield scherm
Overview: This Series 2 platform made the ideal acoustic enclosure for the large AHU and other equipment. It was installed onto single ply with no roof penetrations and 2m high Soundshield acoustic screens to mitigate the sound. Main contractor Morgan Sindall were very happy with this solution on this new modular build A&E for an NHS project.
PROJECT CASE STUDY - Serie 2 met Soundshield
Project: Gants Hill studentenhuisvesting
Project Location: Gants Hill, UK
Client: Tide Construction
Value: £ 36 000.00
Product Description: Series 2 Platform with Soundshield Screens
Overview: This Series 2 platform with 2m high Soundshield acoustic screens to all sides with 2 access doors, was provided for the 6 double VRV condensers. The pedestal feet were placed directly onto the warm roof insulation build-up and the ballast pebbles spread into position after installation of the deck framing.
PROJECT CASE STUDY - Serie 3 met randbeveiliging
Naam van het project: Kantoorgebouw Zurich
Projectlocatie: Swindon, UK
Opdrachtgever: Skanska Construction
Opdrachtsom: £ 13 000,00
Product omschrijving: Platform serie 3 met leuning en 2 x laddertoegang
Overzicht: Onder dit 2 m hoge platform van de serie 3 konden grote leidingen onder het platform worden gelegd, met Guardrail en twee ladders die toegang bieden via zelfsluitende poorten.
PROJECT CASE STUDY - Serie 3 met standaard scherm
Projectnaam: Northern School of Art
Projectlocatie: Middlesbrough
Opdrachtgever: BAM Construction
Opdrachtsom: £ 48 000,00
Productomschrijving: Serie 3 platform met 2,4m hoog Standaardscherm
Overzicht: Dit platform van de serie 3 werd ontworpen ter vervanging van de aanvankelijk meegeleverde stalen platformbehuizing, waardoor veel dakdoorvoeren werden bespaard en de omvang van de dragende stalen constructiedelen onder het dak werd verminderd. Een financieel, structureel voordeel en tijdwinst bij dit project.
PROJECT CASE STUDY - Serie 3 met tussenverdieping en standaard scherm
Projectnaam: John Radcliffe Ziekenhuis
Projectlocatie: Oxford, UK
Opdrachtgever: MTX Contracten
Opdrachtsom: £ 40 000,00
Productomschrijving: Serie 3 Platform met tussenverdieping
Overzicht: Deze oplossing maakte optimaal gebruik van de zeer beperkte ruimte door het toepassen van een tussenverdieping. Deze was toegankelijk via een trapladder met handrail. Onze H-ligger werd gebruikt voor de vrije overspanning. De standaard schermen waren doorlopend aan de buitenkant voor een zeer nette afwerking en afscherming van de apparatuur op beide niveaus.
PROJECT CASE STUDY - Serie 3 met randbeveiliging en constructies voor bovenleidingen
Project: William Harvey Ziekenhuis
Project: Ashford, Kent, UK
Opdrachtgever: MTX Contracten
Waarde: £ 119 000,00
Productomschrijving: Twee serie 3 platformen met bovenliggende kanaalsteunen
Overview: This solution provided for a level working area for the plant and equipment on the 2 roof spaces as well as provision to hang the ductwork from the overhead support structure. The roof had a gradient in 2 directions and steps where the building module connections were.
PROJECT CASE STUDY - Speedscreen met standaard scherm
Naam van het project: One Le Pole Square, kantoorontwikkeling voor gemengd gebruik
Projectlocatie: Dublin, Ierland
Opdrachtgever: JJ Rhatigan Building Contractors
Opdrachtsom: £ 22 360,00
Productomschrijving: Speedscreen-behuizing 2m hoog standaard
Overzicht: Deze 24m lange x 2m hoge vrijstaande Speedscreen omranding wordt bezwaard door betonnen ballastblokken. De installatie werd in 1 dag voltooid en vereiste slechts één kraanlift naar het dak.
PROJECT CASE STUDY - Speedscreen met standaard scherm
Naam van het project: Poole Hospital, operatiekamers
Projectlocatie: Poole, UK
Opdrachtgever: Integrated Health Projects JV
Opdrachtsom: £ 62 760,00
Product omschrijving: Speedscreen overdekking 2,4m hoog standaard
Overzicht: Deze 2,4 m hoge Speedscreen-installatie werd in 4 dagen voltooid en vereiste slechts één kraanlift naar het dak en leverde een omranding op met een totale afmeting van 27 x 10,2 m.
PROJECT CASE STUDY - Speedscreen met Louvre100
Naam van het project: RBK Kingston Dementie Verpleeghuis
Locatie van het project: Kingston, Londen
Opdrachtgever: Integrated Health Projects JV
Opdrachtsom: £ 72 430,00
Productbeschrijving: Speedscreen omranding 3,4m hoog Louvre100
Overview: This 45m long x 3.4m high non-penetrating surface mounted Speedscreen enclosure with louvred finish looked great from the road. There was a 1.5m high parapet, so the louvre stopped at 1.5m above the roof. Three access doors were provided to access in and out of the enclosure. This screen system was installed with all the plant in situ.